Work progress of 1.25 Km road and a bridge construction projects costing 15.5 million AFN in Panjshir province

content_manager
دوشنبه ۱۳۹۹/۷/۷ - ۱۰:۱۶
Work progress of 1.25 Km road and a bridge construction projects costing 15.5 million AFN in Panjshir province

Construction of 1.25 Km road and a 20- meter bridge worth 15.5 million AFN is under process (ongoing) through the National Rural Access Program of MRRD in Qash Daraz Dara-e-Parangal village located in Aabshar district of Panjshir province.

This project will be completed in 263 days, and by its implementation, while solving the transportation problems of 600 families, the villages of Khajeh Khedr, Khyber, Qash Daraz, Sarmeh Qash, Obeh and other neighboring villages will be connected with each other.

تازه خبرونه

چهارشنبه ۱۴۰۳/۹/۷ - ۹:۱
Background image

په کابل کې د کلیو بیا رغونې او پراختیا وزارت سرپرست وزیر الحاج ملا محمد یونس اخندزاده د خپل کار په دفتر کې د ایران هېواد لپاره د افغانستان اسلامي امارت له سفیر مولوي فضل محمد حقاني او مل پلاوي سره وکتل

په دې ناسته کې چې د کلیو د بیارغونې او پراختیا وزارت مالي او اداري مرستیال محترم مولوي عبدالرحمن حلیم صاحب هم ګډون درلود، محترم حقاني صاحب په ګاونډي هېواد ایران کې د مهاجرو افغانانو د. . .

پنجشنبه ۱۴۰۳/۷/۲۶ - ۸:۳۸
Background image

د کلیو د بیارغونې او پراختیا وزارت د کلیو ودانیزو چارو مرستیال معرفي شو

ملا نثاراحمد نصرت چې د افغانستان اسلامي امارت د زعیم عالیقدر امیرالمؤمنین حفظه الله د حکم په اساس د کلیو د بیارغونې او پراختیا وزارت د کلیو ودانیزو چارو د مرستیال په توګه ټاکل شوی وو نن. . .

شنبه ۱۴۰۳/۷/۲۱ - ۱۰:۳۴
Background image

د کليو د بيا رغونې او پراختيا وزارت سرپرست وزیر غور ولايت ته سفر وکړ

د کليو د بيارغونې او پراختيا وزارت سرپرست وزير الحاج ملا محمد يونس اخندزاده او مل پلاوي غور ولايت ته د خپل کاري سفر په ترڅ کې د یاد ولایت د کلیو د بیارغونې او پراختیا ریاست له رئیس او. . .

BACK TO NEWS