Work progress of a water supply network construction project costing 5.21 million AFN in Sar e Pul province
With the total cost of 5.21 million AFN, construction of a water supply network has been 75 % completed by the Ministry of Rural Rehabilitation and Development (MRRD) in Aabjosh and Tekhuch villages of Balkhab district of Sar e pul province.
The mentioned network consists, four iron concrete reservoirs with 10 to 30 cubic meters capacity, four pressure breakers, 100 water taps with total length of 9, 86 kilometers and by the completion of this project, 250 families will gain access to safe drinking water.