Work progress on construction of 7,8 kilometers road project in Panjshear province

Ehsan_admin
Thu, Jun 25 2020 3:30 PM
پنجشیر

With the total cost of 45 million AFN, the construction work of  7,8 kilometers road and it's protective walls, has been 35% completed through the National Rural Access Program of  MRRD in  DarKhanj  village of Esa  e awal district of Panjshear province.

The mentioned project will be completed within 240 days and by it's implementation , Darkhanj,Pawat and Chubak districts will be connected and more than 1957 villagers will be benefited.

Latest news

Tue, Apr 28 2026 8:37 AM
Background image

Coordination Seminar of Central and Provincial Directors Concludes

The three-day coordination seminar for central and provincial directors of the Ministry of Rural Rehabilitation and Development concluded today with a speech by the honorable Al-Haj. . .

Mon, Apr 13 2026 1:51 PM
Background image

Respected Minister of Rural Rehabilitation and Development Meets with International Scholars

Respected Al-Hajj Mullah Abdul Latif Mansoor, Minister of Rural Rehabilitation and Development, met today in his office with scholars from Turkey, Kenya, Burkina Faso, Nigeria,. . .

Mon, Mar 09 2026 1:52 PM
Background image

Meeting between the Honorable Minister of Rehabilitation and Rural Development and the UNICEF Representative

Today, Alhaj Mullah Abdul Latif Mansoor, the Minister of Rehabilitation and Rural Development, met with Dr. Tajudeen Oyewale, the Representative of the UNICEF Office in Afghanistan, and. . .

BACK TO NEWS