Work progress of 120 meters protective wall construction project costing 1.7 million AFN in Laghman province

content_manager
Wed, Sep 16 2020 11:05 AM
په لغمان کې ۱.۷ میلیونه افغانیو په لګښت د ۱۲۰ متره محافظوي دیوال د جوړیدو کار روان دی

Construction of 120 meters protective wall worth 1.7 million AFN has been 70% completed by the Citizens’ Charter National Priority Program of Ministry of Rural Rehabilitation and Development (CCNPP/MRRD) in Maeen Qalha village located in Metarllam district of Laghman province.

During the implementation of this project, 1345 working days have been created for technical and non-technical workers and with its completion, 340 hectares of agricultural land will be protected from the dangers of floods.

Latest news

Thu, Oct 17 2024 8:38 AM
Background image

The Deputy of the Ministry of Rural Rehabilitation and Development Introduced

Mullah Nasir Ahmad Nasrat, who was appointed as the Deputy of Rural Affairs at the Ministry of Rural Rehabilitation and Development by the order of the esteemed Amir al-Muminin of the. . .

Sat, Oct 12 2024 10:34 AM
Background image

The Acting Minister of the Ministry of Rural Rehabilitation and Development traveled to Ghor Province

During his official trip to Ghor Province, Acting Minister of Rural Rehabilitation and Development, Al-Hajj Mullah Mohammad Younus Akhundzada, along with his delegation, met the head. . .

Tue, Oct 01 2024 8:32 AM
Background image

The acting minister of the Ministry of Rural Rehabilitation and Development inaugurated a retaining wall of (5200) meters in Kandahar province

The Ministry of Rural Rehabilitation and Development has completed the construction of a retaining wall measuring (5200) meters in the Spin Boldak district of Kandahar province, at a. . .

BACK TO NEWS