With the total cost of 37 million AFN funded by UNICEF,the construction work of an absorbent water supply network has been 92% completed through the National Water Supply and Sanitation Program of MRRD in immigrants town  which is located in Furozkoh the provincial center of Ghor .

This network has a protective  sarounder ,two springs,  two pressurre  breakers , a concrete reservoir with 300 cubic meters capacity and 1550 miters and is 21 kilobits from springs to reservoir and 24 kilometers pipe inside the immigrants city.

By the construction of the mentioned network ,2000 families will gain access to clean drinking water.

Latest news

Thu, Nov 26 2020 12:04 PM
Background image

Construction of 15 schools completed within two weeks in 9 provinces of the country

Construction of 15 school buildings well-financed by the Education Quality Reform in Afghanistan (EQRA) Project under the Citizens’ Charter National Priority Program of the Ministry of. . .

Wed, Nov 25 2020 2:16 PM
Background image

Construction of a 206- meter protective wall project costing 4.9 million Afghanis completed in Panjshir

Construction of a 206-meter protective wall worth 4.9 million Afghanis has been recently completed and handed over by the Citizens’ Charter National Priority Program of the Ministry of. . .

Tue, Nov 24 2020 2:58 PM
Background image

Implementation of the first water supply project for Kuchi families (nomads) in Paktia province

With the total cost of 500 thousand AFN, implementation of the first water supply project for the Kuchi families (nomads) living in Azadkhel area located Ahmadabad district of Paktia. . .