Work progress on construction of a water supply network in immigrants town of Ghor province

Ehsan_admin
دوشنبه ۱۳۹۹/۴/۹ - ۱۶:۲۱
غور

With the total cost of 37 million AFN funded by UNICEF,the construction work of an absorbent water supply network has been 92% completed through the National Water Supply and Sanitation Program of MRRD in immigrants town  which is located in Furozkoh the provincial center of Ghor .

This network has a protective  sarounder ,two springs,  two pressurre  breakers , a concrete reservoir with 300 cubic meters capacity and 1550 miters and is 21 kilobits from springs to reservoir and 24 kilometers pipe inside the immigrants city.

By the construction of the mentioned network ,2000 families will gain access to clean drinking water.

تازه خبرونه

دوشنبه ۱۴۰۳/۱/۱۳ - ۱۲:۶
Background image

د کلیو د بیارغونې او پراختیا وزارت سرپرست وزیر په افغانستان کې د ملګرو ملتونو د ځانګړي استازي له مرستیال او مل پلاوي سره وکتل

د کلیو د بیارغونې او پراختیا وزارت سرپرست وزیر الحاج ملا محمد یونس آخندزاده نن په خپل کاري دفتر کې په افغانستان کې د ملګرو ملتونو د ځانګړي استازي له مرستیال اندریکا راتوتي او مل پلاوي. . .

پنجشنبه ۱۴۰۳/۱/۲ - ۲۲:۱۲
Background image

په پکتیا ولایت کې یو کوچنی بند ګټې اخیستنې ته وسپارل شو

د کلیو د بیارغونې او پراختیا وزارت له لوري د پکتیا ولایت په زرمت ولسوالۍ کې د څه باندې (۴.۹) میلیونه افغانیو په لګښت د یوه کوچنۍ بند د جوړولو چارې بشپړې او نن د یوې غونډې په ترڅ کې د. . .

شنبه ۱۴۰۳/۱۲/۲۶ - ۹:۳۰
Background image

په کاپيسا ولایت کې (۳۳۱) بیلابیلې پراختیايي پروژې ګټې اخیستنې ته وسپارل شوې

د کلیو د بیارغونې او پراختیا وزارت له لوري او د (UNOPS) دفتر په مالي مرسته د کاپيسا ولایت په حصه اول او حصه دوم ولسوالیو کې د څه باندې (۴۴۱) میلیونه افغانیو په لګښت د افغانستان ټولنیز. . .

BACK TO NEWS