Work progress of a water supply network construction project costing 2,3 million AFN in Balkh
With the total cost of 2,3 million AFN, construction of a water supply network has been 85% completed by the Citizens’ Charter National Priority Program of the Ministry of Rural Rehabilitation and Development in Hasan abad village located in Balkh district of Balkh province .
The network has a length of 1.43 km, a height reserve with a capacity of 23 cubic meters of water, 2 deep wells and 10 water taps.
. It is worth mentioning that during the work of this project, 700 working days have been created for technical and non-technical workers and with its completion, 250 families will gain access to safe drinking water.