Handing over of a water supply network construction project worth 4.6 million AFN in Balkh province

content_manager
Tue, Sep 22 2020 2:34 PM
تکمیل کار ساخت یک شبکه‌ی آبرسانی به ارزش ۴.۶ میلیون افغانی در بلخ

a water supply network construction project costing 4.6 million AFN has been recently completed and handed over by the National Water Supply and Sanitation Program of Ministry of Rural Rehabilitation and Development (MRRD) in Balkhabi village located in Nahr Shahi district of Balkh province.

The network included; a 150- meter deep water well, one concrete reservoir with 20 cubic meters capacity, 30 solar panels, a Surrounding wall, 3,580 km of pipeline and 80 water taps.

During the implementation of the mentioned project 110 working days were created and after its completion, 250 families, that most of them are internally displaced, have gotten access to safe drinking water.

Latest news

Sat, Apr 12 2025 10:19 AM
Background image

244 Various Development Projects in Laghman Province Handed Over for Utilization

The Ministry of Rural Rehabilitation and Development has completed 244 development projects in the Alishing and Badpash districts of Laghman province, with an estimated cost of 278. . .

Sat, Apr 12 2025 10:12 AM
Background image

161 Various Development Projects Launched in Laghman Province

The Ministry of Rural Rehabilitation and Development has initiated 161 development projects in the Alingar district of Laghman province, with an estimated cost of approximately 295. . .

Wed, Mar 26 2025 9:29 AM
Background image

68 Development Projects Launched in Kapisa Province

The Ministry of Rural Rehabilitation and Development has initiated 68 development projects in the Tagab district of Kapisa province, with an estimated cost of approximately 120 million. . .

BACK TO NEWS