Handing over of a water supply network construction project in Parwan province

content_manager
Sun, Aug 23 2020 2:30 PM
تکمیل کار ساخت یک شبکه‌ی آبرسانی به ارزش ۴.۸ میلیون افغانی در پروان

With the total cost of 4,829,000 AFN, a water supply network construction project handed over through The Rural Water Supply and Sanitation Program (Ru-WatSP) of Ministry of Rural Rehabilitation and Development (MRRD) in Dawlat Shahi village in Bagram district of Parwan province.

 The project included the digging of a deep well, construction of a 40-cubic meter water reservoir, installation of a 4, 5-kilometer pipes network, and 242-meter boxes and other essential parts and with its completion around 440 families have gotten access to potable water.

Latest news

Sat, Apr 12 2025 10:19 AM
Background image

244 Various Development Projects in Laghman Province Handed Over for Utilization

The Ministry of Rural Rehabilitation and Development has completed 244 development projects in the Alishing and Badpash districts of Laghman province, with an estimated cost of 278. . .

Sat, Apr 12 2025 10:12 AM
Background image

161 Various Development Projects Launched in Laghman Province

The Ministry of Rural Rehabilitation and Development has initiated 161 development projects in the Alingar district of Laghman province, with an estimated cost of approximately 295. . .

Wed, Mar 26 2025 9:29 AM
Background image

68 Development Projects Launched in Kapisa Province

The Ministry of Rural Rehabilitation and Development has initiated 68 development projects in the Tagab district of Kapisa province, with an estimated cost of approximately 120 million. . .

BACK TO NEWS