Handing over of a Kareaz construction project costing 3 million AFN in Logar province

content_manager
Sat, Sep 05 2020 11:58 AM
په لوګر کې د اوبو لګولو د کاریز پروژه ګټې اخیستنې ته وسپارل شوه

With the total cost of three million AFN, a karez construction project was completed and handed over through the Regional Programs Coordination Office of Ministry of Rural Rehabilitation and Development (MRRD) in Zardad village, the provincial center of Logar .

The project included the construction of 1.528 kilometers Canal, water reservoir and digging of 58 Kareaz wells.

During the implementation of the mentioned project, 1807 working days were created and by its accomplishment 350 hectares of the agricultural lands have been irrigated and more than 1890 residents of the mentioned area have been benefited.

Latest news

Wed, Jun 02 2021 3:10 PM
Background image

42 Families Accessed to Safe Drinking Water in Zabul Province

The Water Sanitation and Hygiene Program under the Ministry of Rural Rehabilitation and Development (MRRD) provided safe drinking water to 42 families in Shahry Safa district of Zabul. . .

Wed, Feb 17 2021 10:11 AM
Background image

Work progress of a 72-meter long bridge worth 39 million Afghanis in Takhar province

 

With the total cost of 39 million AFN. Construction of a 72-meter concrete bridge and a 250-meter connecting road project has been completed by the National Rural Access Program of. . .

Wed, Feb 17 2021 8:38 AM
Background image

Clean drinking water provided for 165 families in Ghor province

with the total cost of 2,330,000 AFN funded through the state budget of Afghanistan,a solar-powered water supply network has been recently constructed and handed over by the Rural Water. . .