Work progress of a bridge and a 136-meter protective wall construction project worth 13 million Afghanis in Sar-e Pul province

content_manager
Mon, Oct 12 2020 2:55 PM
جریان کار ساخت یک پایه پل و ۱۳۶ متر دیوار محافظتی به ارزش ۱۳ میلیون افغانی در سرپل

With the total cost of 13 million AFN, construction of a 13-meter bridge and 136 meters protective wall is under process by the Regional Programs Coordination Office of Ministry of Rural Rehabilitation and Development (MRRD) in Dio Qul Archa toy village located in Sancharak district of Sar-e-Pul province.

The project is scheduled to be implemented within 420 days and after its completion 3000 rural families will be benefited.

Latest news

Mon, Mar 09 2026 1:52 PM
Background image

Meeting between the Honorable Minister of Rehabilitation and Rural Development and the UNICEF Representative

Today, Alhaj Mullah Abdul Latif Mansoor, the Minister of Rehabilitation and Rural Development, met with Dr. Tajudeen Oyewale, the Representative of the UNICEF Office in Afghanistan, and. . .

Wed, Mar 04 2026 12:29 PM
Background image

The Honorable Minister of Rehabilitation and Rural Development met with the Head of the UNDP Office and his accompanying delegation

Today, Alhaj Mala Abdul Latif Mansoor, the Minister of Rehabilitation and Rural Development, met with Mr. Stephen Rodricks, the Head of the UNDP Office, and his accompanying delegation. . .

Mon, Feb 02 2026 9:15 AM
Background image

Coordination Meeting Held Between the Ministry of Rural Rehabilitation and Development and Representatives of Institutions

Today, before noon, under the leadership of the Honorable Minister of Rural Rehabilitation and Development, Al-Haj Mullah Abdul Latif Mansoor, a coordination meeting was held with. . .

BACK TO NEWS